Hi,

Please find the attached screenshots of the project settings, workplan, financial summary pages.

How do we enable such that the labor forecast in financial summary is calculated based on the workplan planned labor costs instead of using a staffing profile?

I know the settings to calculate the Labor from the staffing profile. but I want to calculate the labor forecast from the work plan instead of a staffing profile.

Any help is greatly appreciated. Thanks.

2 REPLIES
Micro Focus Frequent Contributor
Micro Focus Frequent Contributor

Re: Calculate Financial Summary Labor Forecast from workplan

Hello,

My name is Bryan and I will assist you on this thread. 

After a research about this matter, I've found that R&D already closed an Enhancement Request without changes in the application. 

You can check the information in the link below:

https://softwaresupport.softwaregrp.com/group/softwaresupport/search-result/-/facetsearch/document/LID/QCCR1L40517?lang=en&cc=us&hpappid=206728_SSO_PRO

Please let me know your thoughts about this incident. 

Thanks,
Bryan. 

ArunKr Respected Contributor.
Respected Contributor.

Re: Calculate Financial Summary Labor Forecast from workplan

Thanks Bryan. I guess we'll have to wait for next version or some patch to see if MF includes these in their next release