Deleting Resources in MSP controlled workplan and actual hours missing

lynguyenalg
Absent Member.

Deleting Resources in MSP controlled workplan and actual hours missing

Hello - I have a project manager who has deleted a resource (not the task) from their MSP controlled workplan. When they looked at the actual information (hours and cost) the deleted resource's hours and cost were now missing from that task. We use Time Management to collect actuals, so I would have thought it would continue to show on the tasks since the timesheet still shows the actual effort. The resource booked a total of 500 hours to multiple tasks. Now the project cost is skewed with these missing hours.
Please help!
Thanks,
Ly