MS Project Work Around

hasankalim Valued Contributor.
Valued Contributor.

MS Project Work Around

Hello All,

Is there a way other than MS Project Integration to synchronize the % complete? This is a pain point for our PM's as the timesheet data populates our actuals but causes duplicate effort to add the % complete.  We don't have our associates estimating remaining effort.

1 REPLY
Micro Focus Expert
Micro Focus Expert

Re: MS Project Work Around

Hello Kalim,

I hope you’re having a good day.

My name is Adolfo Alvarado from PPM team and I have been assigned to assist your thread related "MS Project Work Around

I was reviewing the "project management configuration guide" document and the page 37,  you can find the steps to configure the actual from the time management, I attached the document. 

Any questions or doubts please let me know 

Best Regards