NOTICE: Certain versions of content (“Material”) accessible here may contain branding from Hewlett-Packard Company (now HP Inc.) and Hewlett Packard Enterprise Company. As of September 1, 2017, the Material is now offered by Micro Focus, a separately owned and operated company. Any reference to the HP and Hewlett Packard Enterprise/HPE marks is historical in nature, and the HP and Hewlett Packard Enterprise/HPE marks are the property of their respective owners.
Project and Portfolio Management User Discussions
cancel

Reporting - YTD Total Hours for a Resource for a Task (Total Hours Roll-up)

YoureGettingADell
New Member

Reporting - YTD Total Hours for a Resource for a Task (Total Hours Roll-up)

I am trying to view how many hours spent on a task for me for the year (Task Rollup by number of hours).  I ran a Time Sheet Summary - Actual Time Summary, but it just gives me the number of hours (Actual Hours) of each Task by week. 

 

Is there any way that it can total each task to give me the combined number of hours for that task for the year?

1 REPLY
 Honored Contributor.. Amishra  Honored Contributor..
 Honored Contributor..

Re: Reporting - YTD Total Hours for a Resource for a Task (Total Hours Roll-up)

G'day, 

Which version of PPM are you on?

You will have to write a custom portlet/ report to achieve this.

Explore TM_ACtuals_Effort table, look for Actual_effort, effort_order column. You can map with TM_ACTUALS and KTMG_PERIODS to get the desired results. 

 